Enercon E92 Turbine – Hill of Lybster Wind Turbine

John Gunn and Sons were subcontracted by Pure Green Consulting for their Civil Engineering Services at a site at Hill of Lybster, Forss in Caithness. The works began in Summer of 2023 and were completed by Spring 2024.

John Gunn and Sons were responsible for the following;

  • Setting Out of all works on-site.
  • Construction of Haul Road and Crane Hardstanding Platform.
  • Construction of E92 Turbine Foundation.
  • Ducting Installation Works.
  • Construction of Switch Room Plinth and AUX Transformer Base.
  • Managing Sub-contractors for the works.

All quarry materials for the works including crushed rock, cable sand and ready-mix concrete were supplied from our quarry at Bower.
The total volume of concrete supplied and installed for the E92 Enercon foundation was 496m3.